New Morgans Development
Coming Soon...


Morgans Group are currently working on an exciting new project that will further develop the maritime quarter in SA1. There will soon be a brand new venue located right on the outskirts of the city centre where customers will be able to enjoy the surrounding beauty of Swansea marina.

The latest developments on the building will be uploaded regulary on this page to enable you to get an insight into what's coming to Swansea soon.

Watch this space!

Development Stage 9 - 09/03/15

  • Final floorboards have gone down on the first floor
  • Staircase joining the 2nd and 3rd floors has been removed
  • Joists have been removed from the exterior wall
  • Interior wall on ground floor has come down with steel framework put in

 

Development Stage 8 - 31/03/15

  • Ground floor walls have come down with steel framework added
  • Work on accessing the basement has begun
  • Room wall has come down with beamwork being put in above
  • Flooring almost complete on the first floor

 

Development Stage 7 - 19/03/15

  • Beams on the first floor have been removed to be replaced
  • Beams on the first floor have been removed to be replaced
  • Floorboards have been laid in one of the proposed rooms
  • Steel framework has gone up with blockwork pillars on the ground floor

 

Development Stage 6 - 06/03/15

  • Flooring has started coming up on the second floor
  • Doorways re-structured and floorboards have started to be laid
  • Supporting framework added to roofing
  • More flooring taking place in one of the proposed rooms

 

Development Stage 5 - 03/03/15

  • Flooring work started on second floor
  • Interior walls started going up on top floor
  • Cementing the walls on the top floor
  • Flooring work complete on top floor

 

Development Stage 4 - 26/02/2015

  • Steel frames gone up ready for internal walls
  • Original flooring beams removed
  • Upper level flooring close to completion
  • More flooring taking place in one of the rooms

 

Development Stage 3 - 23/02/2015

  • Internal framework has started going up
  • Existing flooring has been removed
  • More floorwork is taking place in one of the planned rooms

 

Development Stage 2 - 18/02/15

  • Exterior wall varnished and completed
  • Joists are raised to start flooring upper level

 

Development Stage 1 - 11/02/15